Standing in the storage area-- more walls than yesterday.
Monday, July 28, 2014
Off the Mark
I guess I was a bad class photographer on Monday after work. We headed near the house so we figured we'd swing by. We did see that our basement coat closet was added. The bathroom is also framed in. One issue is that the deck staircase doesn't quite seem to meet up with the concrete where the support will go. We've sent a few messages and 3 days later we still don't know what the correction plan will be for this. I only took one other photos. Odd for me. I'm sure I will make up for it another time.
Sunday, July 27, 2014
Basement Progress
So there is finally some decent progress. The framers have come back and the basement is framed. After looking through on Sunday we called for a coat closet to be added into the basement under the stairs.
| the unfinished portion of basement--for storage |
| Where we decided to add a coat closet. the bathroom will be on the R side |
| looking into the basement office. 2 wide closets in the back |
| Standing in what will be the basement galley kitchen. The sink will go under the window. On the right is the utility room. |
| Trying to figure out where to place the basement TV |
| Looking into the basement family room from the galley kitchen |
| It's really exciting to finally see the deck on the house. |
Saturday, June 21, 2014
Vault is Repaired
Well, not a lot exciting to report this week. 2 of the 3 tubs are sitting in place. The rest of the windows are in. The garage doors and external doors are all in. Some of the plumbing is in. But, we decided to upgrade to Pex plumbing, and they placed PVC instead. So, that will have to be swapped out. Also, the stairs to the basement are in.
| 2 garage doors and the front door all visible |
| The truss issue has now been corrected |
| Lots of important documentation on the sliding glass door |
| This will be where the exhaust vent will vent out through |
| It's pretty cool to see the front door installed, as well as the windows |
| View into the guest room |
| Overlooking the foyer from the loft |
| Some of the drains are in place |
Tuesday, June 10, 2014
In Geometry we Trussed!
So, I will admit that it takes a lot to impress me. I was thrilled to get a lovely email from Steve from Wayne Homes on Saturday night about our concerns and addressing them thoroughly. I was just about floored that in just 3 days we already have a fix lined up for our trusses that is signed off by the engineer.
![]() |
Lastly, it is exciting to hear that all of the other work can continue as planned since the trusses will be repaired in place. So plumbing and HVAC are next on the list.
Saturday, June 7, 2014
All trussed up
So of course after the photo that Steve from Wayne Homes sent us we couldn't wait to get to see the house progress this weekend. We got to walk around the second floor and check out the roof in person. We were a little perplexed at the living room ceiling. We have planned (and paid for) a vaulted living room ceiling. Soooo, long story short we got in touch with Steve who assured us that we were correct, and the roof trusses were the wrong ones for over the living room. This came down to approximately 13 trusses.
| We have tar paper and ice guard on the roof |
| The tub surrounds have arrived |
| The temporary construction stairs. Easy to climb, sketchy to descend. |
| The WRONG trusses. |
| The 2 story foyer. The front door will be in the bottom open area with a plant ledge at the window. |
| The second story framing--very nervewracking trying to make sure that the 3 year old doesn't topple through a window opening. |
| Also of concern is the dampness along this foundation wall. Steve from Wayne Homes is aware and we will be monitoring for it to dry out--- and stay dry. |
| Less damp over here, but still worth mentioning |
Wednesday, June 4, 2014
House on the Lot
I've been thinking that anyone out there checking out this blog may wonder how the house is setting on the property. So here's the layout. We had a variance meeting a few months back to change the build line so that the walkout basement would work the best, as well as maximize the backyard. We had looked at many many pieces of property prior to finding and purchasing this one. We had one bid go through just to find out that the hook up cost would have been prohibitive. We had another lot go to a higher bidder. It was a several month search. Initially we were looking for a much larger amount of land, but we feel that the mature trees and layout should suit us just fine.
Raise the roof!!
So today Steve our project manager from Wayne Homes sent us an email with a photo attached. Most of the roof is up and it really looks like a house. It is so super exciting!!